Building log

22-Aug-2008
Re-assembly..bis
Catégorie: Fuselage : Cabin

The reassembly of the cabin parts goes on. I first verified the torque of all the nuts, mainly tise of the main gear supports.
Then I riveted both fresh air sccops.




Next parts to be reinstalled were the fuel vent lines. A third hand could be used for some of the clamps




Then I riveted the top of the bagage bulkhead wondering why I didn't do it earlier.
I also riveted the upper rib to the next bulkhead,which didn't go as planned, I'll have to drill out the rivets and redo them after the upper skin is installed.




Working time on this subpart
Today :  4h (Total : 174h)