08-Nov-2007
Fuel selector
|
I installed the fuel selector; its an Andair selector looking more robust and safer than the one supplied by Vans. Then I begun working on the rollbar. The part is quite complex and there are four rollbar quarts to be assembled. The two rear parts have to be drilled to 1 1/2 inches. Then two liaising parts have to be fabricated and drilled. I still have some angles to cut and drill before beginning the assembly. Working time on this subpart Today : 2h (Total : 54h) |